Before
Over the years, the coping on our pool had deteriorated. The coping is the material on the top edge surrounding the pool. We also had some tiles that had begun to fall off around the skimmer area. There was a question about whether to repair them or replace them, with the latter being the bigger and more expensive project.
There was also the plan to add a pool safety cover which made the current coping a bit problematic. Our existing coping was both sloped upwards at the end and was very rough. For a pool safety cover that is pulled tight against it, that would leave a gap for debris to get in as well and wear out the cover more easily from the abrasions.
We decided to replace both the coping and tiles and this project became a prerequisite to the Pool Cover Project. We would choose a smooth and flat coping to have the cover better fit, and would choose glass iridescent tiles that were particularly nice looking.
This was not much of a DIY project as it only required us to find the right contractor and pick out the coping and tiles. This worked out well as the contractor did good work and we were happy with the end result. It took a crew of 2 to 5 folks (depending on the day) a full week to complete the project.
Day 1 Progress - Demolition and Emptying
The first day was the demolition of the existing coping and tiles and beginning to empty the pool.
Day 2 Progress - New Coping Begins
The second day saw the installation of the first pieces of coping, the pool finslly being emptied and the delivery of the boxes of new tiles.
Day 3 Progress - New Tiles Begin
This day most of the new coping pieces were all in place and the initial areas of new tiles were put in place.
Day 4 Progress
This was the day the new tiles would be mostly completed and coping was trimmed and smoothed.
Day 5 Progress
The final work day for the crew saw them filling in the tiles that required more intricate cuts (around skimmer and returns). They also did a good job of cleaning up. I was able to beginning filling the pool again after this.
Day 6 Progress
It took more than a full day to refill the pool using two hoses. Also a few hundred dollars in water charges form the city, not to mention the shaming email they sent about how I was using more water than the average person in Austin.
Final
By the evening, the pool was full.
I would then spend the next many days/weeks starting from scratch with the pool chemistry to try to get it back in proper balance.